New leisure centre on site of demolished old leisure centre. The new centre will be run by Birmingham Community Leisure Trust.
The facility includes:
25 metre, 6 lane swimming pool
Training/Learner pool
Changing Facilities
Fitness Studio
Dance Studio
Hannafin Contractors works package included:
· Groundworks
· Earthworks
· 2 Attenuation Tanks
· Reinforced concrete and Foundations
· Drainage - storm and foul water
· Pool construction excluding M&E
· Basement Plant Room
· Externals including kerbs, paving, tarmac, white lining, street furniture and topsoiling
· Cross site Services - Trenching and Ducting and forming service pits and substation base